PJSC Uralkali, Ust-Yaivinsky mine, Berezniki

To see all projects

INFORMATION ABOUT THE OBJECT

The following works were performed by LLC «MC «UES»:
- the 1 turn of gas-turbine station on the fourth (2 turbine units of "Siemens" on 12,9 MW each, 2 recovery coppers with a productivity of 21-24 tons of steam per hour). Input - May, 2008;
- the II turn (2 turbine units on 12,9 MW each and 2 recovery coppers). Input-2010 year;
- a steam boiler room (3 coppers on 35 tons of steam per hour of LOOS firm (Germany));
- reconstruction of the granulation department on the fourth mining department which power is 750 000 tons per year. It will allow to increase power to 1 500 000 tons per year;
- expansion of a salt dump. The area of the I turn is 45 hectares;
- modernization of a mine shaft N1 with replacement of the skip hoist on the second and fourth mining department.